Construction Approaches 50% Completion
With construction advancing on schedule, Eskay Creek is fully permitted and on track to achieve initial production and cash flow in Q2 2027. Skeena is redefining collaborative mine development through strong partnerships and responsible practices, positioning the Company to become one of the world’s lowest-cost precious metals producers.
January 2026
Pre-permitting Construction Progress
During the summers of 2024 and 2025, Skeena advanced substantial early works at Eskay Creek under permit amendments issued by the Province of British Columbia, along with the Bulk Technical Sample permit. These approvals enabled construction to proceed on an accelerated timeline, helping position Eskay Creek for production in the shortest possible timeframe. View the photo gallery for a snapshot of early construction progress from 2024 and 2025.